Project Experience
HAI DUONG GARDEN HOTEL
- Client
- TM VIETNAM DEVELOPMENT CO., LTD.
- Sector
- Hotel / Serviced Apartment
- Location
- Hai Phong
Supporting Renovation and Facility Improvement at Hai Duong Garden
Hai Duong Garden is a hotel and serviced apartment in Hai Phong City, with an eight-storey reinforced concrete structure and an approximate floor area of 6,000 m².
TM Vietnam Development carried out several improvement works at the property, including guest room renovation, wastewater treatment works and pump room repair.
Plus PM Vietnam supported the Client through Site Observation Support and Design Management Consultancy, covering construction monitoring, technical review, schedule follow-up, design coordination and cost review across the different work packages.
The guest room renovation included eight rooms on the third floor and was completed in May 2026.

Project Information
| Client | TM VIETNAM DEVELOPMENT CO., LTD. |
| Location | 54 Do Ngoc Du Street, Hai Phong City (formerly Hai Duong Province), Vietnam |
| Sector | Hotel / Serviced Apartment |
| GFA | Approximately 6,000 m² |
| Structure | Reinforced Concrete (RC) |
| Floors | 8 Floors |
| Guest Room Renovation | 8 rooms on the third floor |
| Design | Masuoka Gumi Co., Ltd. |
| Contractor | Frontier Consulting Vietnam Co., Ltd. |
| Plus PM Services | Site Observation Support / Design Management Consultancy |
Our Services
01 Site Observation Support
Plus PM Vietnam provided Site Observation Support for guest room renovation and pump room repair works.
The scope included reviewing shop drawings, method statements and material submissions, checking on-site construction methods and progress, verifying installed materials, and reporting issues requiring corrective action.
02 Design Management Consultancy
For the wastewater treatment works, Plus PM Vietnam supported Client through design development process.
The scope included reviewing design documents and drawings, coordinating civil, wastewater treatment and MEP requirements, and identifying design conflicts or incomplete information.
03 Schedule and Project Coordination
Plus PM Vietnam monitored design and construction progress against the agreed schedules and followed up on delays or issues requiring action.
The team also attended project meetings and coordinated with Client, contractors and other project parties to support smooth project execution.
04 Cost and Technical Review
As part of the wastewater treatment design management scope, Plus PM Vietnam reviewed construction cost estimates and contractor cost-reduction proposals.
This helped Client consider cost implications together with technical and design requirements during project development.